6.6 Commissioning of Gas Sampling Device
6.6.1 The commissioning of gas sampling device shall meet the following requirements:
1 Run the sampling car and adjust the travel limit switch according to the design documents.
2 Run the sampling car and stop at each specified position,then move to and fro in the whole stroke for at least 3 times,the operation shall be stable and the stop position shall be accurate,the opening/closing operation of the limit switch shall be flexible and reliable.
3 Normally open/close the gas check valve for at least 3 times and the operation shall be flexible and reliable.
4 The cooling water in sampling tube and cooler shall maintain unblocked without leakage.
Check method:observe,measure,check the commissioning records.