7.12 Top Ignition Device
Ⅰ Dominant Items
7.12.1 The gas pipe and oxygen pipe that are connected with the burner shall meet the requirements in the design documents.
Check quantity:full check.
Check method:check the pipe handover records and take visual check.
Ⅱ General Items
7.12.2 The allowable installation deviation of top ignition device shall meet the requirements in Table 7.12.2.
Check quantity:full check.
Check method:see Table 7.12.2.
Table 7.12.2 Allowable installation deviation of top ignition device(mm)